Stream Garland Hyperscale Data Center

Category
Mission Critical
About This Project

CESG has built and serviced numerous data centers for Stream, Cyrus One, DataBank, and others. This hyperscale data center was designed for cloud and enterprise customers. The project sits on 23 acres in Garland, Texas. The building is an expandable 138,132 SF facility with redundant 40 MW utility feeds from an on-site substation provided by Oncor. Our work included electrical installations for site security, site power and telecom conduits, lighting and feeders.

Size
138,132 SF

General Contractor
J.E. Dunn Construction

Completed
2019